PROPOSED CORDELE TRAIN VIEWING PLATFORM

Number of visitors

12902
Total Visitors

City of Cordele Engineering Department

Permitting

We are known as a “City of Progress” for a reason! We welcome new industry and encourage growth. Below are premitting requirements for development within our city:

SITE PLAN REQUIREMENTS, DEVELOPMENT REGULATIONS AND SUBDIVISION REGULATIONS

SITE PLAN SUBMITTAL CHECKLIST, rev 2020 0914

DEVELOPMENT REGULATIONS Cordele

SUBDIVISION REGULATIONS Section 1130

LOW PRESSURE SANITARY SEWER SYSTEMS ARE BECOMING MORE POPULAR AND MORE COST EFFECTIVE. HERE ARE THE REQUIREMENTS APPROVED BY THE CITY OF CORDELE, GEORGIA, FOR LOW PRESSURE SANITARY SEWER SYSTEMS:

DESIGN REQUIREMENTS LOW PRESSURE SEWER

THE CITY OF CORDELE DISCOURAGES DEVELOPMENT WITHIN A FLOOD PLAIN; HOWEVER, WE UNDERSTAND THAT THIS IS SOMETIMES NEEDED. THE LINKS BELOW WILL HELP DEFINE REQUIERMENTS FOR SUCH DEVELOPMENTS: Please note that the below listed floodplain development permit is currently a permit used by staff until the City Commission adopts its own permit. The current permit is developed based on information required and furnished by the State of Georgia.

GENERAL FLOODPLAIN INFORMATION

FLOOD ZONE PERMITTED ITEMS CHECKLIST

FLOODPLAIN DEVELOPMENT PERMIT

 

 

 

 

PROJECTS OUT FOR BID

There are no projects for the engineering department currently out for bid as of July 23, 2020.

PROJECTS UNDER DESIGN

PROJECTS UNDER DESIGN INCLUDE:

Storm Drainage Master Plan. This is an ongoing project.

 

PROJECTS UNDER CONSTRUCTION

PROJECTS UNDER CONSTRUCTION:

NOTE:  These projects only include projects under contract with the City of Cordele, GA and do not include projects by private developers.

Pecan Street Sidewalks. Contract awarded December, 2019, and presently under construction. Expected completion date is September, 2020.

Train Viewing Platform. 

Construction started June 15, 2020. Completion date is scheduled for the middle of December, 2020.

Sanitary Sewer Rehabilitation. The contract for the Sanitary Sewer Rehabilitation of the  Northside Trunk Sewer Line Phase 4 was awarded at the Tuesday night, July 21, 2020, Cordele, Georgia, commission meeting to Instituform Technologies, LLC of Jacksonville, Florida. The project consist of the rehabilitation of approximately 7,952 linear feet of 15-inch sanitary sewer main by the cured-in-place method. NOTICE TO PROCEED  was given with start date of August 24, 2020,with required completion date of not more then 120 days.

Bid Tabulation