PROJECTS OUT FOR BID

There are no projects for the engineering department currently out for bid as of July 23, 2020.

PROJECTS UNDER DESIGN

PROJECTS UNDER DESIGN INCLUDE:

Storm Drainage Master Plan. This is an ongoing project.

 

PROJECTS UNDER CONSTRUCTION

PROJECTS UNDER CONSTRUCTION:

NOTE:  These projects only include projects under contract with the City of Cordele, GA and do not include projects by private developers.

Pecan Street Sidewalks. Contract awarded December, 2019, and presently under construction. Expected completion date is September, 2020.

Train Viewing Platform. 

Construction started June 15, 2020. Completion date is scheduled for the middle of December, 2020.

Sanitary Sewer Rehabilitation. The contract for the Sanitary Sewer Rehabilitation of the  Northside Trunk Sewer Line Phase 4 was awarded at the Tuesday night, July 21, 2020, Cordele, Georgia, commission meeting to Instituform Technologies, LLC of Jacksonville, Florida. The project consist of the rehabilitation of approximately 7,952 linear feet of 15-inch sanitary sewer main by the cured-in-place method. NOTICE TO PROCEED  was given with start date of August 24, 2020,with required completion date of not more then 120 days.

Bid Tabulation